Tag Archives: renewables

Has rooftop solar cost California ratepayers more than the alternatives?

The Energy Institute’s blog has an important premise–that solar rooftop customers have imposed costs on other ratepayers with few benefits. This premise runs counter to the empirical evidence.

First, these customers have deferred an enormous amount of utility-scale generation. In 2005 the CEC forecasted the 2020 CAISO peak load would 58,662 MW. The highest peak after 2006 has been 50,116 MW (in 2017–3,000 MW higher than in August 2020). That’s a savings of 8,546 MW. (Note that residential installations are two-thirds of the distributed solar installations.) The correlation of added distributed solar capacity with that peak reduction is 0.938. Even in 2020, the incremental solar DER was 72% of the peak reduction trend. We can calculate the avoided peak capacity investment from 2006 to today using the CEC’s 2011 Cost of Generation model inputs. Combustion turbines cost $1,366/kW (based on a survey of the 20 installed plants–I managed that survey) and the annual fixed charge rate was 15.3% for a cost of $209/kW-year. The total annual savings is $1.8 billion. The total revenue requirements for the three IOUs plus implied generation costs for DA and CCA LSEs in 2021 was $37 billion. So the annual savings that have accrued to ALL customers is 4.9%. Given that NEM customers are about 4% of the customer base, if those customers paid nothing, everyone else’s bill would only go up by 4% or less than what rooftop solar has saved so far.

In addition, the California Independent System Operator (CAISO) calculated in 2018 that at least $2.6 billion in transmission projects had been deferred through installed distributed solar. Using the amount installed in 2017 of 6,785 MW, the avoided costs are $383/kW or $59/kW-year. This translates to an additional $400 million per year or about 1.1% of utility revenues.

The total savings to customers is over $2.2 billion or about 6% of revenue requirements.

Second, rooftop solar isn’t the most expensive power source. My rooftop system installed in 2017 costs 12.6 cents/kWh (financed separately from our mortgage). In comparison, PG&E’s RPS portfolio cost over 12 cents/kWh in 2019 according to the CPUC’s 2020 Padilla Report, plus there’s an increments transmission cost approaching 4 cents/kWh, so we’re looking at a total delivered cost of 16 cents/kwh for existing renewables. (Note that the system costs to integrate solar are largely the same whether they are utility scale or distributed).

Comparing to the average IOU RPS portfolio cost to that of rooftop solar is appropriate from the perspective of a customer. Utility customers see average, not marginal, costs and average cost pricing is widely prevalent in our economy. To achieve 100% renewable power a reasonable customer will look at average utility costs for the same type of power. We use the same principle by posting on energy efficient appliances the expect bill savings based on utility rates–-not on the marginal resource acquisition costs for the utilities.

And customers who would choose to respond to the marginal cost of new utility power instead will never really see those economic savings because the supposed savings created by that decision will be diffused across all customers. In other words, other customers will extract all of the positive rents created by that choice. We could allow for bypass pricing (which industrial customers get if they threaten to leave the service area) but currently we force other customers to bear the costs of this type of pricing, not shareholders as would occur in other industries. Individual customers are currently the decision making point of view for most energy use purposes and they base those on average cost pricing, so why should we have a single carve out for a special case that is quite similar to energy efficiency?

I wrote more about whether a fixed connection cost is appropriate for NEM customers and the complexity of calculating that charge earlier this week.

Understanding core facts before moving forward with NEM reform

There is a general understanding among the most informed participants and observers that California’ net energy metering (NEM) tariff as originally conceived was not intended to be a permanent fixture. The objective of the NEM rate was to get a nascent renewable energy industry off the ground and now California has more than 11,000 megawatts of distributed solar generation. Now that the distributed energy resources industry is in much less of a need for subsidies, but its full value also must be recognized. To this end it is important to understand some key facts that are sometimes overlooked in the debate.

The true underlying reason for high rates–rising utility revenue requirements

In California, retail electricity rates are so high for two reasons, the first being stranded generation costs and the second being a bunch of “public goods charges” that constitute close to half of the distribution cost. PG&E’s rates have risen 57% since 2009. Many, if not most, NEM customers have installed solar panels as one way to avoid these rising rates. The thing is when NEM 1.0 and 2.0 were adopted, the cost of the renewable power purchase agreements (PPA) portfolios were well over $100/MWH—even $120MWH through 2019, and adding in the other T&D costs, this approached the average system rate as late as 2019 for SCE and PG&E before their downward trends reversed course. That the retail rate skyrocketed while renewable PPAs fell dramatically is a subsequent development that too many people have forgotten.

California uses Ramsey pricing principles to allocate these (the CPUC applies “equal percent marginal costs” or EPMC as a derivative measure), but Ramsey pricing was conceived for one-way pricing. I don’t know what Harold Hotelling would think of using his late student’s work for two way transactions. This is probably the fundamental problem in NEM rates—the stranded and public goods costs are incurred by one party on one side of the ledger (the utility) but the other party (the NEM customer) doesn’t have these same cost categories on the other side of the ledger; they might have their own set of costs but they don’t fall into the same categories. So the issue is how to set two way rates given the odd relationships of these costs and between utilities and ratepayers.

This situation argues for setting aside the stranded costs and public goods to be paid for in some manner other than electric rates. The answer can’t be in a form of a shift of consumption charges to a large access charge (e.g., customer charge) because customers will just leave entirely when half of their current bill is rolled into the new access charge.

The largest nonbypassable charge (NBC), now delineated for all customers, is the power cost indifference adjustment (PCIA). The PCIA is the stranded generation asset charge for the portfolio composed of utility-scale generation. Most of this is power purchase agreements (PPAs) signed within the last decade. For PG&E in 2021 according to its 2020 General Rate Case workpapers, this exceeded 4 cents per kilowatt-hour.

Basic facts about the grid

  • The grid is not a static entity in which there are no changes going forward. Yet the cost of service analysis used in the CPUC’s recent NEM proposed decision assumes that posture. Acknowledging that the system will change going forward depending on our configuration decisions is an important key principle that is continually overlooked in these discussions.
  • In California, a customer is about 15 times more likely to experience an outage due to distribution system problems than from generation/transmission issues. That means that a customer who decides to rely on self-provided resources can have a set up that is 15 times less reliable than the system grid and still have better reliability than conventional service. This is even more true for customers who reside in rural areas.
  • Upstream of the individual service connection (which costs about $10 per month for residential customers based on testimony I have submitted in all three utilities’ rate cases), customers share distribution grid capacity with other customers. They are not given shares of the grid to buy and sell with other customers—we leave that task to the utilities who act as dealers in that market place, owning the capacity and selling it to customers. If we are going to have fixed charges for customers which essentially allocated a capacity share to each of them, those customers also should be entitled to buy and sell capacity as they need it. The end result will be a marketplace which will price distribution capacity on either a daily $ per kilowatt or cents per kilowatt-hour basis. That system will look just like our current distribution pricing system but with a bunch of unnecessary complexity.
  • This situation is even more true for transmission. There most certainly is not a fixed share of the transmission grid to be allocated to each customer. Those shares are highly fungible.

What is the objective of utility regulation: just and reasonable rates or revenue assurance?

At the core of this issue is the question of whether utility shareholders are entitled to largely guaranteed revenues to recover their investments. In a market with some level of competitiveness, the producers face a degree of risk under normal functional conditions (more mundane than wildfire risk)—that is not the case with electric utilities, at least in California. (We cataloged the amount of disallowances for California IOUs in the 2020 cost of capital applications and it was less than one one-hundredth of a percent (0.01%) of revenues over the last decade.) When customers reduce or change their consumption patterns in a manner that reduces sales in a normal market, other customers are not required to pick up the slack—shareholders are. This risk is one of the core benefits of a competitive market, no matter what the degree of imperfection. Neither the utilities or the generators who sell to them under contract face these risks.

Why should we bother with “efficient” pricing if we are pushing the entire burden of achieving that efficiency on customers who have little ability to alter utilities’ investment decisions? Bottom line: if economists argue for “efficient” pricing, they need to also include in that how utility shareholders will participate directly in the outcomes of that efficient pricing without simply shifting revenue requirements to other customers.

As to the intent of the utilities, in my 30 year on the ground experience, the management does not make decisions that are based on “doing good” that go against their profit objective. There are examples of each utility choosing to gain profits that they were not entitled to. We entered into testimony in PG&E’s 1999 GRC a speech by a PG&E CEO talking about how PG&E would exploit the transition period during restructuring to maintain market share. That came back to haunt the state as it set up the conditions for ensuing market manipulation.

Each of these issues have been largely ignored in the debate over what to do about solar rooftop policy and investment going forward. It is time to push these to fore.

What to do about Diablo Canyon?

The debate over whether to close Diablo Canyon has resurfaced. The California Public Utilities Commission, which support from the Legislature, decided in 2018 to close Diablo by 2025 rather than proceed to relicensing. PG&E applied in 2016 to retire the plant rather than relicense due to the high costs that would make the energy uneconomic. (I advised the Joint CCAs in this proceeding.)

Now a new study from MIT and Stanford finds potential savings and emission reductions from continuing operation. (MIT in particular has been an advocate for greater use of nuclear power.) Others have written opinion articles on either side of the issue. I wrote the article below in the Davis Enterprise addressing this issue. (It was limited to 900 words so I couldn’t cover everything.)

IT’S OK TO CLOSE DIABLO CANYON NUCLEAR PLANT
A previous column (by John Mott-Smith) asked whether shutting down the Diablo Canyon nuclear plant is risky business if we don’t know what will replace the electricity it produces. John’s friend Richard McCann offered to answer his question. This is a guest column, written by Richard, a universally respected expert on energy, water and environmental economics.

John Mott-Smith asked several questions about the future of nuclear power and the upcoming closure of PG&E’s Diablo Canyon Power Plant in 2025. His main question is how are we going to produce enough reliable power for our economy’s shift to electricity for cars and heating. The answers are apparent, but they have been hidden for a variety of reasons.
I’ve worked on electricity and transportation issues for more than three decades. I began my career evaluating whether to close Sacramento Municipal Utility District’s Rancho Seco Nuclear Generating Station and recently assessed the cost to relicense and continue operations of Diablo after 2025.
Looking first at Diablo Canyon, the question turns almost entirely on economics and cost. When the San Onofre Nuclear Generating Station closed suddenly in 2012, greenhouse gas emissions rose statewide the next year, but then continued a steady downward trend. We will again have time to replace Diablo with renewables.
Some groups focus on the risk of radiation contamination, but that was not a consideration for Diablo’s closure. Instead, it was the cost of compliance with water quality regulations. The power plant currently uses ocean water for cooling. State regulations required changing to a less impactful method that would have cost several billion dollars to install and would have increased operating costs. PG&E’s application to retire the plant showed the costs going forward would be at least 10 to 12 cents per kilowatt-hour.
In contrast, solar and wind power can be purchased for 2 to 10 cents per kilowatt-hour depending on configuration and power transmission. Even if new power transmission costs 4 cents per kilowatt-hour and energy storage adds another 3 cents, solar and wind units cost about 3 cents, which totals at the low end of the cost for Diablo Canyon.
What’s even more exciting is the potential for “distributed” energy resources, where generation and power management occurs locally, even right on the customers’ premises rather than centrally at a power plant. Rooftop solar panels are just one example—we may be able to store renewable power practically for free in our cars and trucks.
Automobiles are parked 95% of the time, which means that an electric vehicle (EV) could store solar power at home or work during the day and for use at night. When we get to a vehicle fleet that is 100% EVs, we will have more than 30 times the power capacity that we need today. This means that any individual car likely will only have to use 10% of its battery capacity to power a house, leaving plenty for driving the next day.
With these opportunities, rooftop and community power projects cost 6 to 10 cents per kilowatt-hour compared with Diablo’s future costs of 10 to 12 cents.
Distributed resources add an important local protection as well. These resources can improve reliability and resilience in the face of increasing hazards created by climate change. Disruptions in the distribution wires are the cause of more than 95% of customer outages. With local generation, storage, and demand management, many of those outages can be avoided, and electricity generated in our own neighborhoods can power our houses during extreme events. The ad that ran during the Olympics for Ford’s F-150 Lightning pick-up illustrates this potential.
Opposition to this new paradigm comes mainly from those with strong economic interests in maintaining the status quo reliance on large centrally located generation. Those interests are the existing utilities, owners, and builders of those large plants plus the utility labor unions. Unfortunately, their policy choices to-date have led to extremely high rates and necessitate even higher rates in the future. PG&E is proposing to increase its rates by another third by 2024 and plans more down the line. PG&E’s past mistakes, including Diablo Canyon, are shown in the “PCIA” exit fee that [CCA] customers pay—it is currently 20% of the rate. Yolo County created VCEA to think and manage differently than PG&E.
There may be room for nuclear generation in the future, but the industry has a poor record. While the cost per kilowatt-hour has gone down for almost all technologies, even fossil-fueled combustion turbines, that is not true for nuclear energy. Several large engineering firms have gone bankrupt due to cost overruns. The global average cost has risen to over 10 cents per kilowatt-hour. Small modular reactors (SMR) may solve this problem, but we have been promised these are just around the corner for two decades now. No SMR is in operation yet.
Another problem is management of radioactive waste disposal and storage over the course of decades, or even millennia. Further, reactors fail on a periodic basis and the cleanup costs are enormous. The Fukuyama accident cost Japan $300 to $750 billion. No other energy technology presents such a degree of catastrophic failure. This liability needs to be addressed head on and not ignored or dismissed if the technology is to be pursued.

Transmission: the hidden cost of generation

The cost of transmission for new generation has become a more salient issue. The CAISO found that distributed generation (DG) had displaced $2.6 billion in transmission investment by 2018. The value of displacing transmission requirements can be determined from the utilities’ filings with FERC and the accounting for new power plant capacity. Using similar methodologies for calculating this cost in California and Kentucky, the incremental cost in both independent system operators (ISO) is $37 per megawatt-hour or 3.7 cents per kilowatt-hour in both areas. This added cost about doubles the cost of utility-scale renewables compared to distributed generation.

When solar rooftop displaces utility generation, particularly during peak load periods, it also displaces the associated transmission that interconnects the plant and transmits that power to the local grid. And because power plants compete with each other for space on the transmission grid, the reduction in bulk power generation opens up that grid to send power from other plants to other customers.

The incremental cost of new transmission is determined by the installation of new generation capacity as transmission delivers power to substations before it is then distributed to customers. This incremental cost represents the long-term value of displaced transmission. This amount should be used to calculate the net benefits for net energy metered (NEM) customers who avoid the need for additional transmission investment by providing local resources rather than remote bulk generation when setting rates for rooftop solar in the NEM tariff.

  • In California, transmission investment additions were collected from the FERC Form 1 filings for 2017 to 2020 for PG&E, SCE and SDG&E. The Wholesale Base Total Revenue Requirements submitted to FERC were collected for the three utilities for the same period. The average fixed charge rate for the Wholesale Base Total Revenue Requirements was 12.1% over that year. That fixed charge rate is applied to the average of the transmission additions to determine the average incremental revenue requirements for new transmission for the period. The plant capacity installed in California for 2017 to 2020 is calculated from the California Energy Commission’s “Annual Generation – Plant Unit”. (This metric is conservative because (1) it includes the entire state while CAISO serves only 80% of the state’s load and the three utilities serve a subset of that, and (2) the list of “new” plants includes a number of repowered natural gas plants at sites with already existing transmission. A more refined analysis would find an even higher incremental transmission cost.)

Based on this analysis, the appropriate marginal transmission cost is $171.17 per kilowatt-year. Applying the average CAISO load factor of 52%, the marginal cost equals $37.54 per megawatt-hour.

  • In Kentucky, Kentucky Power is owned by American Electric Power (AEP) which operates in the PJM ISO. PJM has a market in financial transmission rights (FTR) that values relieving the congestion on the grid in the short term. AEP files network service rates each year with PJM and FERC. The rate more than doubled over 2018 to 2021 at average annual increase of 26%.

Based on the addition of 22,907 megawatts of generation capacity in PJM over that period, the incremental cost of transmission was $196 per kilowatt-year or nearly four times the current AEP transmission rate. This equates to about $37 per megawatt-hour (or 3.7 cents per kilowatt-hour).

Can Net Metering Reform Fix the Rooftop Solar Cost Shift?: A Response

A response to Severin Borenstein’s post at UC Energy Institute where he posits a large subsidy flowing to NEM customers and proposes an income-based fixed charge as the remedy. Borenstein made the same proposal at a later CPUC hearing.

The CPUC is now considering reforming the current net energy metering (NEM) tariffs in the NEM 3.0 proceeding. And the State Legislature is considering imposing a change by fiat in AB 1139.

First, to frame this discussion, economists are universally guilty of status quo bias in which we (since I’m one) too often assume that changing from the current physical and institutional arrangement is a “cost” in an implicit assumption that the current situation was somehow arrived at via a relatively benign economic process. (The debate over reparations for slavery revolve around this issue.) The same is true for those who claim that NEM customers are imposing exorbitant costs on other customers.

There are several issues to be considered in this analysis.

1) In looking at the history of the NEM rate, the emergence of a misalignment between retail rates that compensate solar customers and the true marginal costs of providing service (which are much more than the hourly wholesales price–more on that later) is a recent event. When NEM 1.0 was established residential rates were on the order of 15 c/kWh and renewable power contracts were being signed at 12 to 15 c/kWh. In addition, the transmission costs were adding 2 to 4 c/kWh. This was the case through 2015; NEM 1.0 expired in 2016. NEM 2.0 customers were put on TOU rates with evening peak loads, so their daytime output is being priced at off peak rates midday and they are paying higher on peak rates for usage. This despite the fact that the difference in “marginal costs” between peak and off wholesale costs are generally on the order of a penny per kWh. (PG&E NEM customers also pay a $10/month fixed charge that is close to the service connection cost.) Calculating the net financial flows is more complicated and deserve that complex look than what can be captured in a simple back of the envelope calculation.

2) If we’re going to dig into subsidies, the first place to start is with utility and power plant shareholders. If we use the current set of “market price benchmarks” (which are problematic as I’ll discuss), out of PG&E’s $5.2 billion annual generation costs, over $2 billion or 40% are “stranded costs” that are subsidies to shareholders for bad investments. In an efficient marketplace those shareholders would have to recover those costs through competitively set prices, as Jim Lazar of the Regulatory Assistance Project has pointed out. One might counter those long term contracts were signed on behalf of these customers who now must pay for them. Of course, overlooking whether those contracts were really properly evaluated, that’s also true for customers who have taken energy efficiency measures and Elon Musk as he moves to Texas–we aren’t discussing whether they also deserve a surcharge to cover these costs. But beyond this, on an equity basis, NEM 1.0 customers at least made investments based on an expectation, that the CPUC did not dissuade them of this belief (we have documentation of how at least one county government was mislead by PG&E on this issue in 2016). If IOUs are entitled to financial protection (and the CPUC has failed to enact the portfolio management incentive specified in AB57 in 2002) then so are those NEM customers. If on the other hand we can reopen cost recovery of those poor portfolio management decisions that have led to the incentive for retail customers to try to exit, THEN we can revisit those NEM investments. But until then, those NEM customers are no more subsidized than the shareholders.

3) What is the true “marginal cost”? First we have the problem of temporal consistency between generation vs. transmission and distribution grid (T&D) costs. Economists love looking at generation because there’s a hourly (or subhourly) “short run” price that coincides nicely with economic theory and calculus. On the other hand, those darn T&D costs are lumpy and discontinuous. The “hourly” cost for T&D is basically zero and the annual cost is not a whole lot better. The current methods debated in the General Rate Cases (GRC) relies on aggregating piecemeal investments without looking at changing costs as a whole. Probably the most appropriate metric for T&D is to calculate the incremental change in total costs by the number of new customers. Given how fast utility rates have been rising over the last decade I’m pretty sure that the “marginal cost” per customer is higher than the average cost–in fact by definition marginal costs must be higher. (And with static and falling loads, I’m not even sure how we calculated the marginal costs per kwh. We can derive the marginal cost this way FERC Form 1 data.) So how do we meld one marginal cost that might be on a 5-minute basis with one that is on a multi-year timeframe? This isn’t an easy answer and “rough justice” can cut either way on what’s the truly appropriate approximation.

4) Even if the generation cost is measured sub hourly, the current wholesale markets are poor reflections of those costs. Significant market distortions prevent fully reflecting those costs. Unit commitment costs are often subsidized through out of market payments; reliability regulation forces investment that pushes capacity costs out of the hourly market, added incremental resources–whether for added load such as electrification or to meet regulatory requirements–are largely zero-operating cost renewables of which none rely on hourly market revenues for financial solvency; in California generators face little or no bankruptcy risk which allows them to underprice their bids; on the flip side, capacity price adders such as ERCOT’s ORDC overprices the value of reliability to customers as a backdoor way to allow generators to recover investments through the hourly market. So what is the true marginal cost of generation? Pulling down CAISO prices doesn’t look like a good primary source of data.

We’re left with the question of what is the appropriate benchmark for measuring a “subsidy”? Should we also include the other subsidies that created the problem in the first place?

How to increase renewables? Change the PCIA

California is pushing for an increase in renewable generation to power its electrification of buildings and the transportation sector. Yet the state maintains a policy that will impede reaching that goal–the power cost indifference adjustment (PCIA) rate discourages the rapidly growing community choice aggregators (CCAs) from investing directly in new renewable generation.

As I wrote recently, California’s PCIA rate charged as an exit fee on departed customers is distorting the electricity markets in a way that increases the risk of another energy crisis similar to the debacle in 2000 to 2001. An analysis of the California Independent System Operator markets shows that market manipulations similar to those that created that crisis likely led to the rolling blackouts last August. Unfortunately, the state’s energy agencies have chosen to look elsewhere for causes.

The even bigger problem of reaching clean energy goals is created by the current structure of the PCIA. The PCIA varies inversely with the market prices in the market–as market prices rise, the PCIA charged to CCAs and direct access (DA) customers decreases. For these customers, their overall retail rate is largely hedged against variation and risk through this inverse relationship.

The portfolios of the incumbent utilities, i.e., Pacific Gas and Electric, Southern California Edison and San Diego Gas and Electric, are dominated by long-term contracts with renewables and capital-intensive utility-owned generation. For example, PG&E is paying a risk premium of nearly 2 cents per kilowatt-hour for its investment in these resources. These portfolios are largely impervious to market price swings now, but at a significant cost. The PCIA passes along this hedge through the PCIA to CCAs and DA customers which discourages those latter customers from making their own long term investments. (I wrote earlier about how this mechanism discouraged investment in new capacity for reliability purposes to provide resource adequacy.)

The legacy utilities are not in a position to acquire new renewables–they are forecasting falling loads and decreasing customers as CCAs grow. So the state cannot look to those utilities to meet California’s ambitious goals–it must incentivize CCAs with that task. The CCAs are already game, with many of them offering much more aggressive “green power” options to their customers than PG&E, SCE or SDG&E.

But CCAs place themselves at greater financial risk under the current rules if they sign more long-term contracts. If market prices fall, they must bear the risk of overpaying for both the legacy utility’s portfolio and their own.

The best solution is to offer CCAs the opportunity to make a fixed or lump sum exit fee payment based on the market value of the legacy utility’s portfolio at the moment of departure. This would untie the PCIA from variations in the future market prices and CCAs would then be constructing a portfolio that hedges their own risks rather than relying on the implicit hedge embedded in the legacy utility’s portfolio. The legacy utilities also would have to manage their bundled customers’ portfolio without relying on the cross subsidy from departed customers to mitigate that risk.

The PCIA is heading California toward another energy crisis

The California ISO Department of Market Monitoring notes in its comments to the CPUC on proposals to address resource adequacy shortages during last August’s rolling blackouts that the number of fixed price contracts are decreasing. In DMM’s opinion, this leaves California’s market exposed to the potential for greater market manipulation. The diminishing tolling agreements and longer term contracts DMM observes is the result of the structure of the power cost indifference adjustment (PCIA) or “exit fee” for departed community choice aggregation (CCA) and direct access (DA) customers. The IOUs are left shedding contracts as their loads fall.

The PCIA is pegged to short run market prices (even more so with the true up feature added in 2019.) The PCIA mechanism works as a price hedge against the short term market values for assets for CCAs and suppresses the incentives for long-term contracts. This discourages CCAs from signing long-term agreements with renewables.

The PCIA acts as an almost perfect hedge on the retail price for departed load customers because an increase in the CAISO and capacity market prices lead to a commensurate decrease in the PCIA, so the overall retail rate remains the same regardless of where the market moves. The IOUs are all so long on their resources, that market price variation has a relatively small impact on their overall rates.

This situation is almost identical to the relationship of the competition transition charge (CTC) implemented during restructuring starting in 1998. Again, energy service providers (ESPs) have little incentive to hedge their portfolios because the CTC was tied directly to the CAISO/PX prices, so the CTC moved inversely with market prices. Only when the CAISO prices exceeded the average cost of the IOUs’ portfolios did the high prices become a problem for ESPs and their customers.

As in 1998, the solution is to have a fixed, upfront exit fee paid by departing customers that is not tied to variations in future market prices. (Commissioner Jesse Knight’s proposal along this line was rejected by the other commissioners.) By doing so, load serving entities (LSEs) will be left to hedging their own portfolios on their own basis. That will lead to LSEs signing more long term agreements of various kinds.

The alternative of forcing CCAs and ESP to sign fixed price contracts under the current PCIA structure forces them to bear the risk burden of both departed and bundled customers, and the IOUs are able to pass through the risks of their long term agreements through the PCIA.

California would be well service by the DMM to point out this inherent structural problem. We should learn from our previous errors.

Advanced power system modeling need not mean more complex modeling

A recent article by E3 and Form Energy in Utility Dive calls for more granular temporal modeling of the electric power system to better capture the constraints of a fully-renewable portfolio and the requirements for supporting technologies such as storage. The authors have identified the correct problem–most current models use a “typical week” of loads that are an average of historic conditions and probabilistic representations of unit availability. This approach fails to capture the “tail” conditions where renewables and currently available storage are likely to be sufficient.

But the answer is not a full blown hour by hour model of the entire year with many permutations of the many possibilities. These system production simulation models already take too long to run a single scenario due to the complexity of this giant “transmission machine.” Adding the required uncertainty will cause these models to run “in real time” as some modelers describe it.

Instead a separate analysis should first identify the conditions under which renewables + current technology storage are unlikely to meet demand sufficiently. These include drought that limits hydropower, extreme weather, and extended weather that limits renewable production. Then these conditions can input into the current models to assess how the system responds.

The two important fixes which has always been problem in these models are to energy-limited resources and unit commitment algorithms. Both of these are complex problems, and these models have not done well in scheduling seasonal hydropower pondage storage and in deciding which units to commit to meet a high demand several days ahead. (And these problems are also why relying solely on hourly bulk power pricing doesn’t give an accurate measure of the true market value of a resource.) But focusing on these two problems is much easier than trying to incorporating the full range of uncertainty for all 8,760 hours for at least a decade into the future.

We should not confuse precision with accuracy. The current models can be quite precise on specific metrics such as unit efficiency as different load points, but they can be inaccurate because they don’t capture the effect of load and fuel price variations. We should not be trying to achieve spurious precision through more complete granular modeling–we should be focusing on accuracy in the narrow situations that matter.

CAISO doesn’t quite grasp what led to rolling blackouts

Steve Berberich, CEO of the California Independent System Operator, assessed for GTM  his views on the reasons for the rolling blackouts in the face of a record setting heat wave. He overlooked a key reason for the delay on capacity procurement (called “resource adequacy” or RA) and he demonstrated a lack of understanding of how renewables and batteries will integrate to provide peak capacity.

Berberich is unwilling to acknowledge that at least part of the RA procurement problem was created by CAISO’s unwillingness to step in as a residual buyer in the RA market, which then created resistance by the CCAs to putting the IOUs in that role. RA procurement was delayed at least a year due to CAISO’s reluctance. CAISO appears to be politically tone-deaf to the issues being raised by CCAs on system procurement.

He says that solar will have to be overbuilt to supply energy to batteries for peak load. But that is already the case with the NQC ELCC just a fraction of the installed solar and wind capacity. Renewable capacity above the ELCC is available to charge the batteries for later use. The only question then is how much energy is required from the batteries to support the peak load and is that coming from existing renewables fleet. The resource adequacy paradigm has changed (more akin to the old PNW hydro system) in which energy, not built capacity is becoming the constraint.

Levelized costs are calculated correctly

The Utility Dive recently published an opinion article that claimed that the conventional method of calculating the levelized cost of energy (LCOE) is incorrect. The UD article was derived from an article published in 2019 in the Electricity Journal by the same author, James Loewen. The article claimed that conventional method gave biased results against more capital intensive generation resources such as renewables compared to fossil fueled ones. I wrote a comment to the Electricity Journal showing the errors in Loewen’s reasoning and further reinforcing the rationale for the conventional LCOE calculation. (You have until August 9 to download my article for free.)

I was the managing consultant that assisted the California Energy Commission (CEC) in preparing one of the studies (CEC 2015) referenced in Loewen. I also led the preparation of three earlier studies that updated cost estimates. (CEC 2003, CEC 2007, CEC 2010) In developing these models, the consultants and staff discussed extensively this issue and came to the conclusion that the LCOE must be calculated by discounting both future cashflows and future energy production. Only in this way can a true comparison of discounted energy values be made.

The error in Loewen’s article arises from a misconception that money is somehow different and unique from all other goods and services. Money serves three roles in the economy: as a medium of exchange, as a unit of account, and as a store of value. At its core, money is a commodity used predominantly as an intermediary in the barter economy and as a store of value until needed later. (We can see this particularly when currency was generally backed by a specific commodity–gold.) Discounting derives from the opportunity cost of holding, and not using, that value until a future date. So discounting applies to all resources and services, not just to money.

Blanchard and Fischer (1989) at pp. 70-71, describe how “utility” (which is NOT measured in money) is discounted in economic analysis. Utility is gained by consumption of goods and services. Blanchard and Fischer has an extensive discussion of the marginal rate of substitution between two periods. Again, note there is no discussion of money in this economic analysis–only the consumption of goods and services in two different time periods. That means that goods and services are being discounted directly. The LCOE must be calculated in the same manner to be consistent with economic theory.

We should be able to recover the net present value of project cost by multiplying the LCOE by the generation over the economic life of the project. We only get the correct answer if we use the conventional LCOE.  I walk through the calculation demonstrating this result in the article.