Tag Archives: CCA

We’ve already paid for Diablo Canyon

As I wrote last week, PG&E is proposing that a share of Diablo Canyon nuclear plant output be allocated to community choice aggregators (CCAs) as part of the resolution of issues related to the Integrated Resource Plan (IRP), Resource Adequacy (RA) and Power Charge Indifference Adjustment (PCIA) rulemakings. While the allocation makes sense for CCAs, it does not solve the problem that PG&E ratepayers are paying for Diablo Canyon twice.

In reviewing the second proposed settlement on PG&E costs in 1994, we took a detailed look at PG&E’s costs and revenues at Diablo. Our analysis revealed a shocking finding.

Diablo Canyon was infamous for increasing in cost by more than ten-fold from the initial investment to coming on line. PG&E and ratepayer groups fought over whether to allow $2.3 billion dollars.  The compromise in 1988 was to essentially shift the risk of cost recovery from ratepayers to PG&E through a power purchase agreement modeled on the Interim Standard Offer Number 4 contract offered to qualifying facilities (but suspended as oversubscribed in 1985).

However, the contract terms were so favorable and rich to PG&E, that Diablo costs negatively impacted overall retail rates. These costs were a key contributing factor that caused industrial customers to push for deregulation and restructuring. As an interim solution in 1995 in anticipation of forthcoming restructuring, PG&E and ratepayer groups arrived at a new settlement that moved Diablo Canyon back into PG&E’s regulated ratebase, earning the utilities allowed return on capital. PG&E was allowed to keep 100% of profit collected between 1988 and 1995. The subsequent 1996 settlement made some adjustments but arrived at essentially the same result. (See Decision 97-05-088.)

While PG&E had borne the risks for seven years, that was during the plant startup and its earliest years of operation.  As we’ve seen with San Onofre NGS and other nuclear plants, operational reliability is most at risk late in the life of the plant. PG&E’s originally took on the risk of recovering its entire investment over the entire life of the plant.  The 1995 settlement transferred the risk for recovering costs over the remaining life of the plant back to ratepayers. In addition, PG&E was allowed to roll into rate base the disputed $2.3 billion. This shifted cost recovery back to the standard rate of depreciation over the 40 year life of the NRC license. In other words, PG&E had done an end-run on the original 1988 settlement AND got to keep the excess profits.

The fact that PG&E accelerated its investment recovery over the first seven years and then shifted recovery risk to ratepayers implies that PG&E should be allowed to recover only the amount that it would have earned at a regulated return under the original 1988 settlement. This is equal to the discounted net present value of the net income earned by Diablo Canyon, over both the periods of the 1988 (PPA) and 1995 settlements.

In 1996, we calculated what PG&E should be allowed to recover in the settlement given this premise.  We assumed that PG&E would be allowed to recover the disputed $2.3 billion because it had taken on that risk in 1988, but the net income stream should be discounted at the historic allowed rate of return over the seven year period.  Based on these assumptions, PG&E had recovered its entire $7.7 billion investment by October 1997, just prior to the opening of the restructured market in March 1998.  In other words, PG&E shareholders were already made whole by 1998 as the cost recovery for Diablo was shifted back to ratepayers.  Instead the settlement agreement has caused ratepayers to pay twice for Diablo Canyon.

PG&E has made annual capital additions to continue operation at Diablo Canyon since then and a regulated return is allowed under the regulatory compact.  Nevertheless, the correct method for analyzing the potential loss to PG&E shareholders from closing Diablo is to first subtract $5.1 billion from the plant in service, reducing the current ratebase to capital additions incurred since 1998. This would reduces the sunk costs that are to be recovered in rates from $31 to $3 per megawatt-hour.

Note that PG&E shareholders and bondholders have earned a weighted return of approximately 10% annually on this $5.1 billion since 1998. The compounded present value of that excess return was $18.1 billion by 2014 earned by PG&E.

CCAs don’t undermine their mission by taking a share of Diablo Canyon

Northern California community choice aggregators (CCAs) are considering whether to accept an offer from PG&E to allocate a proportionate share of its “large carbon-free” generation as a credit against the power charge indifference adjustment (PCIA) exit fee.  The allocation would include a share of Diablo Canyon power. The allocation for 2019 and 2020; an extension of this allocation is being discussed on the PCIA rulemaking.

The proposal faces opposition from anti-nuclear and local community activists who point to the policy adopted by many CCAs not to accept any nuclear power in their portfolios. However, this opposition is misguided for several reasons, some of which are discussed in this East Bay Community Energy staff report.

  • The CCAs already receive and pay for nuclear generation as part of the mix of “unspecified” power that the CCAs buy through the California Independent System Operator (CAISO). The entire cost of Diablo Canyon is included in the Total Portfolio Cost used to calculate the PCIA. The CCAs receive a “market value” credit against this generation, but the excess cost of recovering the investment in Diablo Canyon (for which PG&E is receiving double payment based on calculations I made in 1996) is recovered through the PCIA. The CCAs can either continue to pay for Diablo through the PCIA without receiving any direct benefits, or they can at least gain some benefits and potentially lower their overall costs. (CCAs need to be looking at their TOTAL generation costs, not just their individual portfolio, when resource planning.)
  • Diablo Canyon is already scheduled to close Unit 1 in 2024 and Unit 2 in 2025 after a contentious proceeding. This allocation is unlikely to change this decision as PG&E has said that the relicensed plant would cost in excess of $100 per megawatt-hour, well in excess of its going market value. I have written extensively here about how costly nuclear power has been and has yet to show that it can reduce those costs. Unless the situation changes significantly, Diablo Canyon will close then.
  • Given that Diablo is already scheduled for closure, the California Public Utilities Commission (CPUC) is unlikely to revisit this decision. But even so, a decision to either reopen A.16-08-006 or to open a new rulemaking or application would probably take close to a year, so the proceeding probably would not open until almost 2021. The actual proceeding would take up to a year, so now we are to 2022 before an actual decision. PG&E would have to take up to a year to plan the closure at that point, which then takes us to 2023. So at best the plant closes a year earlier than currently scheduled. In addition, PG&E still receives the full payments for its investments and there is likely no capital additions avoided by the early closure, so the cost savings would be minimal.

Microgrids could cost 10% of undergrounding PG&E’s wires

One proposed solution to reducing wildfire risk is for PG&E to put its grid underground. There are a number of problems with undergrounding including increased maintenance costs, seismic and flooding risks, and problems with excessive heat (including exploding underground vaults). But ignoring those issues, the costs could be exorbitant-greater than anyone has really considered. An alternative is shifting rural service to microgrids. A high-level estimate shows that using microgrids instead could cost less than 10% of undergrounding the lines in regions at risk. The CPUC is considering a policy shift to promote this type of solution and has new rulemaking on promoting microgrids.

We can put this in context by estimating costs from PG&E’s data provided in its 2020 General Rate Case, and comparing that to its total revenue requirements. That will give us an estimate of the rate increase needed to fund this effort.

PG&E has about 107,000 miles of distribution voltage wires and 18,500 in transmission lines. PG&E listed 25,000 miles of distribution lines being in wildfire risk zones. The the risk is proportionate for transmission this is another 4,300 miles. PG&E has estimated that it would cost $3 million per mile to underground (and ignoring the higher maintenance and replacement costs). And undergrounding transmission can cost as much as $80 million per mile. Using estimates provided to the CAISO and picking the midpoint cost adder of four to ten times for undergrounding, we can estimate $25 million per mile for transmission is reasonable. Based on these estimates it would cost $75 billion to underground distribution and $108 billion for transmission, for a total cost of $183 billion. Using PG&E’s current cost of capital, that translates into annual revenue requirement of $9.1 billion.

PG&E’s overall annual revenue requirement are currently about $14 billion and PG&E has asked for increases that could add another $3 billion. Adding $9.1 billion would add two-thirds (~67%) to PG&E’s overall rates that include both distribution and generation. It would double distribution rates.

This begs two questions:

  1. Is this worth doing to protect properties in the affected urban-wildlands interface (UWI)?
  2. Is there a less expensive option that can achieve the same objective?

On the first question, if we look the assessed property value in the 15 counties most likely to be at risk (which includes substantial amounts of land outside the UWI), the total assessed value is $462 billion. In other words, we would be spending 16% of the value of the property being protected. The annual revenue required would increase property taxed by over 250%, going from 0.77% to 2.0%.

Which turns us to the second question. If we assume that the load share is proportionate to the share of lines at risk, PG&E serves about 18,500 GWh in those areas. The equivalent cost per unit for undergrounding would be $480 per MWh.

The average cost for a microgrid in California based on a 2018 CEC study is $3.5 million per megawatt. That translates to $60 per MWh for a typical load factor. In other words a microgrid could cost one-eighth of undergrounding. The total equivalent cost compared to the undergrounding scenario would be $13 billion. This translates to an 8% increase in PG&E rates.

To what extent should we pursue undergrounding lines versus shifting to microgrid alternatives in the WUI areas? Should we encourage energy independence for these customers if they are on microgrids? How should we share these costs–should locals pay or should they be spread over the entire customer base? Who should own these microgrids: PG&E or CCAs or a local government?

 

 

 

 

End the fiction of regulatory oversight of California’s generation

1542383922472

M.Cubed is the only firm willing to sign the non-disclosure agreements (NDA) that allow us to review the investor-owned utilities’ (IOUs) generation portfolio data on behalf of outside intervenors, such as the community choice aggregators (CCAs). Even the direct access (DA) customers who constitute about a quarter of California’s industrial load are represented by a firm that is unwilling to sign the NDAs. This situation places departed load customers, and in fact all customers, at a distinct disadvantage when trying to regulate the actions of the IOUs. It is simply impossible for a single small firm to scrutinize all of the filings and data from the IOUs. (Not to mention that one, SDG&E, gets a complete free pass for now as that it has no CCAs.)

This situation has arisen because the NDAs require that the “reviewing representatives” not be in a position to advise market participants, such as CCAs or energy service providers (ESPs) that sell to DA customers, on procurement decisions. This is an outgrowth of AB 57 in 2002, a state law passed to bring IOUs back into the generation market after the collapse of restructuring in 2001. That law was intended to the balance of power to the IOUs away from generators for procurement purposes. Now it puts the IOUs at a competitive advantage against other load serving entities (LSEs) such as CCAs and ESPs, and even bundled customers.

This imbalance has arisen for several insurmountable reasons:

  • No firm can build its business on serving only to review IOU filings without offering other procurement consulting services to clients.
  • It is difficult to build expertise for reviewing IOU filings without participating in procurement services for other LSEs or resource providers. (I am uniquely situated by the consulting work I did for the CEC on assessing generation technology costs for over a decade.)
  • CPUC staff similarly lacks the expertise for many of the same reasons, and are relatively ineffective at these reviews. The CPUC is further limited by its ability to recruit sufficient qualified staff for a variety of reasons.

If California wants to rein in the misbehavior by IOUs (such as what I’ve documented on past procurement and shareholder returns earlier), then we have two options to address this problem going forward:

  1. Transform at least the power generation management side of the IOUs into publicly owned entities with more transparent management review.
  2. End the annual review and setting of PCIA and CTC rates by establishing one-time prepayment amounts. By prepaying or setting a fixed annual amount, the impact of accounting maneuvers are diminished substantially, and since IOUs can no longer shift portfolio management risks to departed load customers, the IOUs more directly face the competitive pressures that should make them more efficient managers.

Exit fee market benchmarks threaten CCAs abilities to meet long term obligations

Capacity Net Revenue Adequacy 2001-2018CCAs may have to choose between complying with the long-term commitments specified in Senate Bill 350 and continuing to operate because they cannot acquire resources at the specified market price benchmarks that value the entire utility portfolio according to the CPUC.

The chart above compares the revenue shortfalls that need to be made up from other capacity sales products to finance resource additions. The CAISO has reported for every year since 2001 that its short-run market clearing prices that were adopted as the market price benchmark in the PCIA have been insufficient to support new conventional generation investment. The chart above shows the results of the CAISO Annual Report on Market Issues and Performance compiled from 2012 to 2018, separated by north (NP15 RRQ) and south (SP15 RRQ) revenue requirements for new resources. (The historic data shows that CAISO revenues have never been sufficient to finance a resource addition.) The CAISO signs capacity procurement (CPM) agreements to meet near-term reliability shortfalls which is one revenue source for a limited number of generators. The other short run price is the resource adequacy credits transacted by load serving entities (LSE) such as the utilities and CCAs. This revenue source is available to a broader set of resources. However, neither of revenues come close to closing the cost shortfall for new capacity.

The CPUC and the CAISO have deliberately suppressed these market prices to avoid the price spikes and reliability problems that occurred during the 2000-2001 energy crisis. By explicit state policy, these market prices are not to be used for assessing resource acquisition benchmarks. Yet, the CPUC adopted in its PCIA OIR decision (D.18-10-019) exactly this stance by asserting that the CCAs must be able to acquire new resources at less than these prices to beat the benchmarks used to calculate the PCIA. The CPUC used the CAISO energy prices plus the average RA prices as the base for the market value benchmark that represents the CCA threshold.

In a functioning market, the relevant market prices should indicate the relative supply-demand balance–if supply is short then prices should rise sufficiently to cover the cost of new entrants. Based on the relative price balance in the chart, no new capacity resources should be needed for some time.

Yet the CPUC recently issued a decision (D.19-04-040) that ordered procurement of 2,000 MW of capacity for resource adequacy. And now the CPUC proposes to up that target to 4,000 MW by 2021. All of this runs counter to the price signals that CPUC claims represent the “market value” of the assets held by the utilities.

If the CCAs purchase resources that cost more than the PCIA benchmarks then they will be losing money for their ratepayers (note that CCAs have no shareholders). Most often long-term power purchase agreements (PPA) have prices above the short-term prices because those short-term prices do not cover all of the values transacted in the market place. (More on that in the near future.) The CPUC should either align its market value benchmarks with its resource acquisition directives or acknowledge that their directives are incorrect.

PG&E has cost California over $3 billion by mismanaging its RPS portfolio

CCA Savings

When community choice aggregators take up serving PG&E customers, PG&E saves the cost of having to procure power for the departed load. Instead the CCAs bear that cost for that power. The savings to PG&E’s bundled customers are not fully reflected when calculating the exit fee (known as the power charge indifference adjustment or PCIA) for those CCAs. As a result, the exit fee does not reflect the true value that CCAs provide to PG&E and its bundled customers.

The chart above shows the realized and potential savings to PG&E from the departure of CCA customers. The realized part is the avoided costs of procuring resources to meet that load, shown in yellow. The second part is the foregone sales opportunity if PG&E had sold a portion of its portfolio to the CCAs at the going price when they departed. In 2019, these combined savings could have reached $3.2 billion if PG&E had acted prudently.

Many local governments launched CCAs to address their climate goals, and CCAs issued multiple requests for offers of RPS energy.  However, PG&E failed to respond to this opportunity to sell excess renewable energy no longer needed to serve their customers.  By deciding to hold these unneeded resources in a declining market, PG&E accumulated additional losses every year.  Indeed, the assigned Judge on the exit-fee proceeding at the CPUC concluded that PG&E must benefit from “holding back the RECs [renewable energy credits] for some reason.”

This willingness to hold onto an unneeded resource that loses value every year is contrary to prudent management.  However, shareholders, are shielded entirely from contract that are too costly, and only pay penalties for failing to meet RPS targets.  Instead, ratepayers—both bundled and CCA—pay all of the excessive costs, and shareholders only have a strong incentive to over-procure using those ratepayer dollars to avoid any possibility of reduced shareholder profits.  Holding these contracts also inflates the exit-fee departed customers must pay, making it harder for alternatives like public power and distributed generation to PG&E to thrive.

When Sonoma Clean Power launched in 2014, the average price of RPS energy was $128/MWh.  It has declined every year, and now sits at $57/MWh.  PG&E’s decision to not sell excess energy at 2014 prices, and to protect shareholders at the expense of ratepayers has cost customers over $3 billion dollars in the last 6 years as shown in the green columns below.  As RPS prices continue to decline, and the amount of customer departing increases, this figure will continue to increase every year.  Indeed, it surpassed $1.1 billion for 2019 alone.

PGAE Mismanagement Costs

Further, the hedging value of the RPS resources that PG&E listed as key attribute of holding these PPAs instead of disposing of them has diminished dramatically since PG&E pushed that as its strategy in its 2014 Bundled Procurement Plan. As shown in the chart above, the hedge value fell $1.3 billion from 2014 to 2019, from a high of $961 million to a burden of $343 million. PG&E’s hedge now adds $33/MWH to the cost of its renewables portfolio.

In comparison, Southern California Edison’s renewables portfolio costs just under $20/MWH less than PG&E’s. SCE did not rush into signing PPAs like PG&E and did not sign them for as long of terms as PG&E.

 

VCEA offers PG&E $300 million for Yolo County

vce_logo_color_white-border

Valley Clean Energy Alliance made its official offer to PG&E to acquire the Yolo County distribution system for $300 million. The offer is being submitted in PG&E’s bankruptcy proceeding. This offer is substantially higher than the $108 million that Sacramento Municipal Utility District (SMUD) offered in 2005, and not far below the $400 million that PG&E countered with.

San Francisco offered $2.5 billion for PG&E’s system, and San Jose announced that it also will make a bid. Municipalities believe that the bankruptcy court will be more receptive to accepting the offers as a means of raising cash for the bankrupt utility.